ITAC Assessment: ME0282
ITAC logo
ITAC Assessment: ME0282
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Fiber Extrusion
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $10
M
to 50
M
# of Employees 83
Plant Area 45,000
ft2
Annual Production 20,500,000
lb
Production Hrs. Annual 8,400
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $855,458 9,936,987
kWh
Electricity Demand $236,287 31,547
kW-mo/yr
LPG $139,448 27,975
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $101,097 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $95,156

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Water Disposal Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $80,666 $36,000 $97,580
1,394,490
kWh
$14,740
-
kW-mo/yr
$(-31,654.0)
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,760 $8,904 $3,088
44,256
kWh
$672
-
kW-mo/yr
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,228 $250 $2,228
31,946
kWh
- - -
04 2.7241: Install outside air damper / economizer on hvac unit $2,181 $4,360 $2,181
31,067
kWh
- - -
05 3.4151: Minimize water usage $12,262 $1,000 - - - $12,262
-
Tgal
TOTAL RECOMMENDED $101,097 $50,514 $105,077
1,501,759
kWh
$15,412
-
kW-mo/yr
$(-31,654.0)
-
MMBtu
$12,262
-
Tgal
TOTAL IMPLEMENTED $95,156 $37,250 $99,808
1,426,436
kWh
$14,740
-
kW-mo/yr
$(-31,654.0)
-
MMBtu
$12,262
-
Tgal
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs