Assessment Year | 2000 |
---|---|
Principal Product | Fiber Extrusion |
NAICS |
n/a
|
SIC | 3081: Unsupported Plastics Film and Sheet |
Sales Range | $10 M to 50M |
# of Employees | 83 |
Plant Area |
45,000
ft2
|
Annual Production | 20,500,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $855,458 | 9,936,987 |
kWh
|
$0.086 |
Electricity Demand | $236,287 | 31,547 |
kW-mo/yr
|
$7.49 |
LPG | $139,448 | 27,975 |
MMBtu
|
$4.98 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $101,097 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $95,156 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $80,666 | $36,000 |
$97,580
1,394,490
kWh
|
$14,740
-
kW-mo/yr
|
$(-31,654.0)
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,760 | $8,904 |
$3,088
44,256
kWh
|
$672
-
kW-mo/yr
|
- | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,228 | $250 |
$2,228
31,946
kWh
|
- | - | - | |
04 | 2.7241: Install outside air damper / economizer on hvac unit | $2,181 | $4,360 |
$2,181
31,067
kWh
|
- | - | - | |
05 | 3.4151: Minimize water usage | $12,262 | $1,000 | - | - | - |
$12,262
-
Tgal
|
|
TOTAL RECOMMENDED | $101,097 | $50,514 |
$105,077
1,501,759
kWh
|
$15,412
-
kW-mo/yr
|
$(-31,654.0)
-
MMBtu
|
$12,262
-
Tgal
|
||
TOTAL IMPLEMENTED | $95,156 | $37,250 |
$99,808
1,426,436
kWh
|
$14,740
-
kW-mo/yr
|
$(-31,654.0)
-
MMBtu
|
$12,262
-
Tgal
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs