| Assessment Year | 1999 |
|---|---|
| Principal Product | cassettes |
| NAICS |
n/a
|
| SIC | 3695: Magnetic And Optical Recording Media |
| Sales Range | $10 M to 50M |
| # of Employees | 280 |
| Plant Area |
105,000
ft2
|
| Annual Production | 70,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $540,497 | 13,874,854 |
kWh
|
$0.039 |
| Electricity Demand | $192,453 | 31,430 |
kW-mo/yr
|
$6.12 |
| Electricity Fees | $(-80,622.0) | - |
|
- |
| LPG | $2,210 | 145 |
MMBtu
|
$15.24 |
| Fuel Oil #2 | $12,809 | 2,789 |
MMBtu
|
$4.59 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,102 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,390 | $39,936 | n/a |
$11,188
279,894
kWh
|
$3,202
-
kW-mo/yr
|
- | - | - | - | - |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,953 | $100 | n/a |
$5,953
148,886
kWh
|
- | - | - | - | - | - |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $5,910 | $450 | n/a |
$5,910
147,714
kWh
|
- | - | - | - | - | - |
| 04 | 4.821: Pay bills on time to avoid late fees | $5,835 | - | n/a | - | - | - | - | - | $5,835 | - |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $3,411 | $2,247 | n/a |
$2,579
64,478
kWh
|
$3,672
-
kW-mo/yr
|
$(-2,840.0)
-
MMBtu
|
- | - | - | - |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $3,237 | $9,562 | n/a | - | - | - |
$3,237
-
MMBtu
|
- | - | - |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,859 | $100 | n/a |
$2,859
71,512
kWh
|
- | - | - | - | - | - |
| 08 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $2,680 | $3,920 | n/a |
$2,680
67,116
kWh
|
- | - | - | - | - | - |
| 09 | 2.4133: Use most efficient type of electric motors | $2,522 | $5,068 | n/a |
$2,085
52,462
kWh
|
$437
-
kW-mo/yr
|
- | - | - | - | - |
| 10 | 2.8121: Apply for tax-free status for energy purchases | $1,892 | - | n/a | - | - | - | - | - | $1,892 | - |
| 11 | 2.8121: Apply for tax-free status for energy purchases | $163 | - | n/a | - | - | - | - | - | $163 | - |
| 12 | 3.4154: Eliminate leaks in water lines and valves | $250 | $100 | n/a | - | - | - | - |
$108
-
Tgal
|
- |
$142
-
Tgal
|
| TOTAL RECOMMENDED | $49,102 | $61,483 |
$33,254
832,062
kWh
|
$7,311
-
kW-mo/yr
|
$(-2,840.0)
-
MMBtu
|
$3,237
-
MMBtu
|
$108
-
Tgal
|
$7,890 |
$142
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs