ITAC Assessment: ME0270
ITAC logo
ITAC Assessment: ME0270
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Newspapers
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $1
M
to 5
M
# of Employees 90
Plant Area 130,000
ft2
Annual Production 1,250,000
pieces
Production Hrs. Annual 2,500
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $22,691 349,355
kWh
Electricity Demand $13,306 1,540
kW-mo/yr
Electricity Fees $4,859 -
Fuel Oil #2 $3,881 1,010
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $9,191 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $5,830 $13,187 $3,583
60,082
kWh
$2,247
-
kW-mo/yr
- - -
02 2.8121: Apply for tax-free status for energy purchases $1,661 - - - - - $1,661
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $654 $200 $654
10,258
kWh
- - - -
04 2.2511: Insulate bare equipment $316 $804 - - $316
-
MMBtu
- -
05 3.5313: Increase amount of waste recovered for resale $730 - - - - $730
-
lb
-
TOTAL RECOMMENDED $9,191 $14,191 $4,237
70,340
kWh
$2,247
-
kW-mo/yr
$316
-
MMBtu
$730
-
lb
$1,661
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs