ITAC Assessment: ME0263
ITAC logo
ITAC Assessment: ME0263
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product rotor blades
NAICS
n/a
SIC 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units
Sales Range $10
M
to 50
M
# of Employees 290
Plant Area 151,682
ft2
Annual Production 982
pieces
Production Hrs. Annual 6,000
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $467,127 6,191,090
kWh
Electricity Demand $93,992 24,700
kW-mo/yr
Electricity Fees $2,168 -
LPG $1,923 45
MMBtu
Fuel Oil #2 $59,515 17,382
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,533 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $31,190

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #2 Savings Other Liquid (haz) Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $17,192 $800 $17,192
215,123
kWh
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $16,457 $45,260 $13,469
168,523
kWh
$2,988
-
kW-mo/yr
- - - -
03 4.652: Replace existing equipment with more suitable substitutes $10,208 $4,185 $7,215
89,977
kWh
$2,993
-
kW-mo/yr
- - - -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $3,320 $4,374 $3,030
37,808
kWh
$1,204
-
kW-mo/yr
$(-914.0)
-
MMBtu
- - -
05 2.2691: Shut off cooling if cold outside air will cool process $2,567 $3,410 $2,567
32,239
kWh
- - - - -
06 2.4133: Use most efficient type of electric motors $2,243 $2,041 $1,896
23,740
kWh
$347
-
kW-mo/yr
- - - -
07 2.4322: Use or replace with energy efficient substitutes $788 $375 $788
9,965
kWh
- - - - -
08 4.821: Pay bills on time to avoid late fees $507 - - - - - - $507
09 2.2511: Insulate bare equipment $211 $205 - - - $211
-
MMBtu
- -
10 3.7214: Reduce or eliminate waste $1,040 $150 - - - - $1,040
-
gal
-
TOTAL RECOMMENDED $54,533 $60,800 $46,157
577,375
kWh
$7,532
-
kW-mo/yr
$(-914.0)
-
MMBtu
$211
-
MMBtu
$1,040
-
gal
$507
TOTAL IMPLEMENTED $31,190 $7,176 $26,303
328,840
kWh
$3,340
-
kW-mo/yr
- - $1,040
-
gal
$507
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings Fuel Oil #2 Savings Other Liquid (haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs