| Assessment Year | 1999 |
|---|---|
| Principal Product | chlorine |
| NAICS |
n/a
|
| SIC | 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 68 |
| Plant Area |
151,682
ft2
|
| Annual Production | 65,456
ton
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $400,000 | 8,616,647 |
kWh
|
$0.046 |
| Electricity Fees | $1,200 | - |
|
- |
| Fuel Oil #2 | $141,591 | 33,225 |
MMBtu
|
$4.26 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,432 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $18,075 | $400 | n/a | - |
$18,075
-
MMBtu
|
- | - |
| 02 | 2.4133: Use most efficient type of electric motors | $13,608 | $48,407 | n/a |
$13,608
289,566
kWh
|
- | - | - |
| 03 | 2.2136: Install / repair insulation on steam lines | $3,246 | $680 | n/a | - |
$3,246
-
MMBtu
|
- | - |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,670 | $100 | n/a |
$2,670
56,858
kWh
|
- | - | - |
| 05 | 2.2511: Insulate bare equipment | $2,332 | $865 | n/a | - |
$2,332
-
MMBtu
|
- | - |
| 06 | 4.821: Pay bills on time to avoid late fees | $1,883 | - | n/a | - | - | $1,883 | - |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $564 | $1,078 | n/a |
$564
12,016
kWh
|
- | - | - |
| 08 | 2.2135: Repair and eliminate steam leaks | $1,054 | $260 | n/a | - |
$1,026
-
MMBtu
|
- |
$28
-
Tgal
|
| TOTAL RECOMMENDED | $43,432 | $51,790 |
$16,842
358,440
kWh
|
$24,679
-
MMBtu
|
$1,883 |
$28
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #2 Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs