ITAC Assessment: ME0238
ITAC logo
ITAC Assessment: ME0238
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Truck Bodies and Cranes
NAICS
n/a
SIC 3713: Truck and Bus Bodies
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 16,160
ft2
Annual Production 2,000
units
Production Hrs. Annual 2,548
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $14,543 199,004
kWh
Electricity Demand $8,757 1,008
kW-mo/yr
Electricity Fees $588 -
Natural Gas $20,157 2,703
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,927 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,254

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7495: Install replacement doors $4,297 $8,000 - - - $4,297
-
MMBtu
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,607 $17,669 $2,367
33,705
kWh
$1,240
-
kW-mo/yr
- - - - -
03 2.7491: Insulate glazing, walls, ceilings, and roofs $2,854 $10,432 - - - $2,854
-
MMBtu
- - -
04 2.7491: Insulate glazing, walls, ceilings, and roofs $1,583 $3,576 - - - $1,583
-
MMBtu
- - -
05 2.7232: Replace existing hvac unit with high efficiency model $747 $2,209 - - - $747
-
MMBtu
- - -
06 2.8114: Change rate schedules or other changes in utility service $306 $1,090 $(-123.0)
(-1,758)
kWh
$(-46.0)
-
kW-mo/yr
$535 - - - $(-60.0)
07 2.8123: Pay utility bills on time $176 - - - - $176
-
MMBtu
- - -
08 2.8123: Pay utility bills on time $87 - - - $87 - - - -
09 3.6124: Burn waste oil for heat $2,633 $21,500 - - - $2,633
-
MMBtu
- - -
10 3.5146: Utilize a central coolant system for cleaning and reuse of metal working fluid $1,637 - $(-37.0)
(-586)
kWh
$(-126.0)
-
kW-mo/yr
- - $2,400
-
gal
$(-600.0)
-
lb
-
TOTAL RECOMMENDED $17,927 $64,476 $2,207
31,361
kWh
$1,068
-
kW-mo/yr
$622 $12,290
-
MMBtu
$2,400
-
gal
$(-600.0)
-
lb
$(-60.0)
TOTAL IMPLEMENTED $6,254 $19,878 $2,330
33,119
kWh
$1,114
-
kW-mo/yr
$87 $923
-
MMBtu
$2,400
-
gal
$(-600.0)
-
lb
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs