| Assessment Year | 1997 |
|---|---|
| Principal Product | Custom Wood Turning |
| NAICS |
n/a
|
| SIC | 2499: Wood Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 80 |
| Plant Area |
70,800
ft2
|
| Annual Production | 30,000,000
pieces
|
| Production Hrs. Annual | 2,400
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $84,407 | 1,366,061 |
kWh
|
$0.062 |
| Electricity Demand | $34,609 | 5,001 |
kW-mo/yr
|
$6.92 |
| Electricity Fees | $4,375 | - |
|
- |
| Fuel Oil #1 | $2,306 | 341 |
MMBtu
|
$6.76 |
| Fuel Oil #2 | $6,961 | 1,252 |
MMBtu
|
$5.56 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $68,461 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $64,712 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $2,370 | - | - | - | - | - | $2,370 | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,367 | $7,625 |
$1,570
22,567
kWh
|
$797
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.2511: Insulate bare equipment | $981 | $1,602 | - | - |
$981
-
MMBtu
|
- | - | - | |
| 04 | 2.8121: Apply for tax-free status for energy purchases | $452 | - | - | - | - | - | $452 | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $420 | $300 |
$420
7,034
kWh
|
- | - | - | - | - | |
| 06 | 2.4221: Install compressor air intakes in coolest locations | $401 | $250 |
$401
6,741
kWh
|
- | - | - | - | - | |
| 07 | 2.8121: Apply for tax-free status for energy purchases | $150 | - | - | - | - | - | $150 | - | |
| 08 | 2.8123: Pay utility bills on time | $119 | - | - | - | - | - | $119 | - | |
| 09 | 3.1191: Change procedures / equipment / operating conditions | $59,587 | $43,304 | - | - | - | - | - | $59,587 | |
| 10 | 3.7214: Reduce or eliminate waste | $1,614 | $50 | - | - | - |
$1,614
-
gal
|
- | - | |
| TOTAL RECOMMENDED | $68,461 | $53,131 |
$2,391
36,342
kWh
|
$797
-
kW-mo/yr
|
$981
-
MMBtu
|
$1,614
-
gal
|
$3,091 | $59,587 | ||
| TOTAL IMPLEMENTED | $64,712 | $43,654 |
$420
7,034
kWh
|
- | - |
$1,614
-
gal
|
$3,091 | $59,587 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Wood Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs