Assessment Year | 1997 |
---|---|
Principal Product | cardboard containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
165,000
ft2
|
Annual Production | 650,000,000
thousand feet
|
Production Hrs. Annual | 6,860
hrs
|
Location (State) | Maine |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $201,859 | 3,558,910 |
kWh
|
$0.057 |
Electricity Demand | $89,044 | 11,594 |
kW-mo/yr
|
$7.68 |
Electricity Fees | $121 | - |
|
- |
Natural Gas | $116,891 | 30,772 |
MMBtu
|
$3.80 |
LPG | $12,832 | 1,538 |
MMBtu
|
$8.34 |
Fuel Oil #2 | $15,946 | 3,795 |
MMBtu
|
$4.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $99,430 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $62,444 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $25,155 | $8,223 |
$20,160
335,873
kWh
|
$11,059
-
kW-mo/yr
|
$(-3,389.0)
-
MMBtu
|
$(-2,675.0)
-
MMBtu
|
- | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,912 | $32,046 |
$14,551
242,380
kWh
|
$3,361
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.4239: Eliminate or reduce compressed air usage | $7,434 | $1,980 |
$7,434
123,974
kWh
|
- | - | - | - | - | - | - | - | |
04 | 2.2511: Insulate bare equipment | $5,853 | $925 |
$5,853
97,597
kWh
|
- | - | - | - | - | - | - | - | |
05 | 2.6212: Turn off equipment during breaks, reduce operating time | $2,583 | $486 |
$2,583
43,083
kWh
|
- | - | - | - | - | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,024 | - |
$2,024
33,705
kWh
|
- | - | - | - | - | - | - | - | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $930 | $30 |
$930
15,533
kWh
|
- | - | - | - | - | - | - | - | |
08 | 2.7291: Reschedule and rearrange multiple-source heating systems | $662 | - |
$524
8,792
kWh
|
$138
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
09 | 2.2136: Install / repair insulation on steam lines | $432 | $91 |
$432
26,671
kWh
|
- | - | - | - | - | - | - | - | |
10 | 3.1193: Convert from batch operation to continuous processing | $36,223 | $200,000 | - | - | - | - | - |
$443
-
lb
|
$28,500 | $7,280 | - | |
11 | 3.4151: Minimize water usage | $222 | $110 | - | - | - | - |
$185
-
Tgal
|
- | - | - |
$37
-
Tgal
|
|
TOTAL RECOMMENDED | $99,430 | $243,891 |
$54,491
927,608
kWh
|
$14,558
-
kW-mo/yr
|
$(-3,389.0)
-
MMBtu
|
$(-2,675.0)
-
MMBtu
|
$185
-
Tgal
|
$443
-
lb
|
$28,500 | $7,280 |
$37
-
Tgal
|
||
TOTAL IMPLEMENTED | $62,444 | $233,062 |
$22,860
400,353
kWh
|
$3,361
-
kW-mo/yr
|
- | - | - |
$443
-
lb
|
$28,500 | $7,280 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs