| Assessment Year | 1995 |
|---|---|
| Principal Product | Electrical componants |
| NAICS |
n/a
|
| SIC | 3643: Current-Carrying Wiring Devices |
| Sales Range | $50 M to 100M |
| # of Employees | 300 |
| Plant Area |
21,000
ft2
|
| Annual Production | 150,000,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $760,853 | 8,648,593 |
kWh
|
$0.088 |
| Natural Gas | $270,880 | 46,856 |
MMBtu
|
$5.78 |
| LPG | $5,615 | 241 |
MMBtu
|
$23.30 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $90,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,302 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $34,808 | $109,189 |
$34,808
485,932
kWh
|
- | - | - | - | - | |
| 02 | 2.4239: Eliminate or reduce compressed air usage | $12,532 | $1,125 |
$12,532
179,074
kWh
|
- | - | - | - | - | |
| 03 | 2.4239: Eliminate or reduce compressed air usage | $5,640 | $1,417 |
$5,640
80,598
kWh
|
- | - | - | - | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,019 | $600 |
$4,019
57,444
kWh
|
- | - | - | - | - | |
| 05 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,610 | $5,000 |
$4,774
33,998
kWh
|
$(-164.0)
-
MMBtu
|
- | - | - | - | |
| 06 | 2.8113: Purchase gas directly from a contract gas supplier | $3,000 | $500 | - | - | - | - | $3,000 | - | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $1,630 | $1,800 |
$1,630
23,154
kWh
|
- | - | - | - | - | |
| 08 | 2.8121: Apply for tax-free status for energy purchases | $550 | - | - | - | - | - | $550 | - | |
| 09 | 2.1233: Analyze flue gas for proper air/fuel ratio | $411 | $400 | - |
$411
-
MMBtu
|
- | - | - | - | |
| 10 | 2.2153: Close off unneeded steam lines | $12,433 | - | - |
$11,788
-
MMBtu
|
$354
-
Tgal
|
- | - |
$291
-
Tgal
|
|
| 11 | 3.3132: Use reverse osmosis to concentrate material | $4,998 | $3,500 | - | - | - |
$4,998
-
gal
|
- | - | |
| 12 | 3.4151: Minimize water usage | $4,333 | $1,300 | - | - |
$2,379
-
Tgal
|
- | - |
$1,954
-
Tgal
|
|
| 13 | 3.4151: Minimize water usage | $1,618 | $440 | - |
$843
-
MMBtu
|
$490
-
Tgal
|
- | - |
$285
-
Tgal
|
|
| TOTAL RECOMMENDED | $90,582 | $125,271 |
$63,403
860,200
kWh
|
$12,878
-
MMBtu
|
$3,223
-
Tgal
|
$4,998
-
gal
|
$3,550 |
$2,530
-
Tgal
|
||
| TOTAL IMPLEMENTED | $33,302 | $9,882 |
$26,965
351,114
kWh
|
$679
-
MMBtu
|
$2,869
-
Tgal
|
- | $550 |
$2,239
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs