| Assessment Year | 1994 |
|---|---|
| Principal Product | Tungsten filaments |
| NAICS |
n/a
|
| SIC | 3496: Miscellaneous Fabricated Wire Products |
| Sales Range | $10 M to 50M |
| # of Employees | 200 |
| Plant Area |
94,000
ft2
|
| Annual Production | 1,000,000,000
pieces
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $350,958 | 4,550,410 |
kWh
|
$0.077 |
| Fuel Oil #6 | $36,698 | 13,762 |
MMBtu
|
$2.67 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,417 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $2,688 | $4,500 |
$2,688
-
kWh
|
- | |
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $18,453 | $6,650 |
$25,000
268,757
kWh
|
$(-6,547.0)
-
MMBtu
|
|
| 03 | 2.5196: Use small number of high output units instead of many small inefficient units | $5,276 | $7,200 |
$5,276
68,288
kWh
|
- | |
| TOTAL RECOMMENDED | $26,417 | $18,350 |
$32,964
337,045
kWh
|
$(-6,547.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs