| Assessment Year | 1994 |
|---|---|
| Principal Product | Lumber |
| NAICS |
n/a
|
| SIC | 2421: Sawmills and Planing Mills, General |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
76,000
ft2
|
| Annual Production | 75,000
thousand feet
|
| Production Hrs. Annual | 2,500
hrs
|
| Location (State) | Maine |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,064,445 | 13,534,877 |
kWh
|
$0.079 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $757,090 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,084 | $7,000 |
$5,398
68,581
kWh
|
- |
$(-1,314.0)
-
MMBtu
|
|
| 02 | 2.3416: Use combined cycle gas turbine generator sets with waste heat boilers connected to turbine exhaust | $690,090 | $1,600,000 |
$690,090
6,278,429
kWh
|
- | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $61,130 | $41,000 |
$61,130
776,671
kWh
|
- | - | |
| 04 | 2.2437: Recover waste heat from equipment | $1,786 | $900 | - |
$1,786
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $757,090 | $1,648,900 |
$756,618
7,123,681
kWh
|
$1,786
-
MMBtu
|
$(-1,314.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs