ITAC Assessment: ME0129
ITAC logo
ITAC Assessment: ME0129
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Textiles
NAICS
n/a
SIC 2231: Broadwoven Fabric Mills, Wool (Including Dyeing and Finishing)
Sales Range $10
M
to 50
M
# of Employees 275
Plant Area 185,000
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 7,000
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $566,467 6,178,195
kWh
LPG $74,789 11,068
MMBtu
Fuel Oil #6 $80,918 34,633
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,751 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,317

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings LPG Savings Fuel Oil #6 Savings
01 2.4322: Use or replace with energy efficient substitutes $5,142 $5,400 $5,142
55,979
kWh
- -
02 2.2437: Recover waste heat from equipment $770 $900 - - $770
-
MMBtu
03 2.4133: Use most efficient type of electric motors $20,700 $19,600 $20,700
225,674
kWh
- -
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $13,522 $3,800 $19,725
215,123
kWh
$(-6,203.0)
-
MMBtu
-
05 2.2136: Install / repair insulation on steam lines $1,617 $880 - - $1,617
-
MMBtu
TOTAL RECOMMENDED $41,751 $30,580 $45,567
496,776
kWh
$(-6,203.0)
-
MMBtu
$2,387
-
MMBtu
TOTAL IMPLEMENTED $22,317 $20,480 $20,700
225,674
kWh
- $1,617
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs