ITAC Assessment: ME0113
ITAC logo
ITAC Assessment: ME0113
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Machine Shop/Foundry
NAICS
n/a
SIC 3366: Copper Foundries
Sales Range $10
M
to 50
M
# of Employees 20
Plant Area 28,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,100
hrs
Location (State) Maine

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,809 203,693
kWh
LPG $1,198 77
MMBtu
Fuel Oil #6 $20,796 5,644
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $3,782 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,782

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Fuel Oil #2 Savings Fuel Oil #6 Savings
01 2.2136: Install / repair insulation on steam lines $599 $471 - $599
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $845 $1,000 - $845
-
MMBtu
-
03 2.1311: Replace electrically-operated equipment with fossil fuel equipment $1,592 $3,500 $1,790
14,654
kWh
- $(-198.0)
-
MMBtu
04 2.1311: Replace electrically-operated equipment with fossil fuel equipment $412 $950 $486
5,275
kWh
- $(-74.0)
-
MMBtu
05 2.1213: Direct warmest air to combustion intake $334 $400 - $334
-
MMBtu
-
TOTAL RECOMMENDED $3,782 $6,321 $2,276
19,929
kWh
$1,778
-
MMBtu
$(-272.0)
-
MMBtu
TOTAL IMPLEMENTED $3,782 $6,321 $2,276
19,929
kWh
$1,778
-
MMBtu
$(-272.0)
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs