ITAC Assessment: MAS020
ITAC logo
ITAC Assessment: MAS020
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2012
Principal Product Butter and Milk Products
NAICS 311511: Fluid Milk Manufacturing
SIC 2026: Fluid Milk
Sales Range $50
M
to 100
M
# of Employees 75
Plant Area 78,000
ft2
Annual Production 106,000,000
lb
Production Hrs. Annual 7,488
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $939,616 10,623,360
kWh
Electricity Demand $307,529 24,942
kW-mo/yr
Natural Gas $1,241,796 135,603
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $79,862 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,042

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $32,764 $7,000 $32,764
370,363
kWh
-
02 2.2414: Use waste heat from hot flue gases to preheat $29,617 $60,000 - $29,617
-
MMBtu
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $11,203 $7,700 $11,203
126,728
kWh
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $4,667 $11,600 $4,667
52,797
kWh
-
05 2.2162: Reduce excess steam bleeding $1,611 $500 - $1,611
-
MMBtu
TOTAL RECOMMENDED $79,862 $86,800 $48,634
549,888
kWh
$31,228
-
MMBtu
TOTAL IMPLEMENTED $39,042 $19,100 $37,431
423,160
kWh
$1,611
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs