Assessment Year | 2012 |
---|---|
Principal Product | Shaft Seals |
NAICS | 339991: Gasket, Packing, and Sealing Device Manufacturing |
SIC | 3053: Gaskets, Packing, and Sealing Devices |
Sales Range | $50 M to 100M |
# of Employees | 241 |
Plant Area |
35,000
ft2
|
Annual Production | 23,400,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,085,083 | 8,652,976 |
kWh
|
$0.13 |
Electricity Demand | $147,792 | 21,265 |
kW-mo/yr
|
$6.95 |
Natural Gas | $133,185 | 14,380 |
MMBtu
|
$9.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $179,086 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $83,121 | $172,430 |
$75,115
599,000
kWh
|
$8,006
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $22,975 | $6,000 |
$22,975
183,210
kWh
|
- | - | |
03 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $29,548 | $92,700 |
$27,544
219,648
kWh
|
$2,004
-
kW-mo/yr
|
- | |
04 | 2.7314: Reduce ventilation air | $19,133 | $2,100 |
$5,706
45,500
kWh
|
- |
$13,427
-
MMBtu
|
|
05 | 2.6218: Turn off equipment when not in use | $10,200 | $1,775 |
$10,200
81,344
kWh
|
- | - | |
06 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $6,270 | $22,500 |
$6,270
49,998
kWh
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,027 | - |
$2,109
16,819
kWh
|
$1,918
-
kW-mo/yr
|
- | |
08 | 2.6241: Reduce temperature of process equipment when on standby | $2,045 | $4,600 |
$2,045
16,307
kWh
|
- | - | |
09 | 2.6218: Turn off equipment when not in use | $1,767 | - |
$1,767
14,092
kWh
|
- | - | |
TOTAL RECOMMENDED | $179,086 | $302,105 |
$153,731
1,225,918
kWh
|
$11,928
-
kW-mo/yr
|
$13,427
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs