| Assessment Year | 2023 |
|---|---|
| Principal Product | Municipal Wastewater Treatment |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $1 M to 5M |
| # of Employees | 2 |
| Plant Area |
20,000
ft2
|
| Annual Production | 14,292
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $49,773 | 308,640 |
kWh
|
$0.16 |
| Electricity Demand | $8,428 | 696 |
kW-mo/yr
|
$12.11 |
| Electricity Fees | $360 | - |
|
- |
| Fuel Oil #2 | $20,137 | 700 |
MMBtu
|
$28.77 |
| TOTAL YEARLY COSTS | $78,698 | |||
| RECOMMENDED SAVINGS* | $10,534 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7226: Use computer programs to optimize hvac performance | $6,991 | $1,650 | - | - |
$6,991
-
MMBtu
|
|
| 02 | 3.1191: Change procedures / equipment / operating conditions | $1,955 | $500 |
$1,773
11,010
kWh
|
$182
-
kW-mo/yr
|
- | |
| 03 | 2.7234: Use heat pump for space conditioning | $1,588 | $5,500 |
$1,322
8,212
kWh
|
$266
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $10,534 | $7,650 |
$3,095
19,222
kWh
|
$448
-
kW-mo/yr
|
$6,991
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs