Assessment Year | 2023 |
---|---|
Principal Product | Water treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $500 k to 1M |
# of Employees | 4 |
Plant Area |
14,800
ft2
|
Annual Production | 53,642
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $94,459 | 516,400 |
kWh
|
$0.18 | |
Electricity Demand | $34,873 | 1,184 |
kW-mo/yr
|
$29.45 | |
Other Energy | $9,694 | 299 |
MMBtu
|
$32.42 | |
Waste Disposal Costs | |||||
Water Usage | $8,234 | 1,168 |
Tgal
|
$7.05 | |
TOTAL YEARLY COSTS | $147,260 | ||||
RECOMMENDED SAVINGS* | $72,441 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $29,333 | $216,701 |
$21,176
115,715
kWh
|
- | $8,157 | |
02 | 2.4322: Use or replace with energy efficient substitutes | $27,331 | $166,000 |
$22,376
122,276
kWh
|
$4,955
-
kW-mo/yr
|
- | |
03 | 2.7234: Use heat pump for space conditioning | $12,269 | $11,300 |
$9,618
52,560
kWh
|
$2,651
-
kW-mo/yr
|
- | |
04 | 2.7234: Use heat pump for space conditioning | $3,098 | $5,000 |
$2,038
11,134
kWh
|
$1,060
-
kW-mo/yr
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $204 | $264 |
$116
633
kWh
|
$88
-
kW-mo/yr
|
- | |
06 | 3.1191: Change procedures / equipment / operating conditions | $106 | $375 |
$106
580
kWh
|
- | - | |
07 | 3.1191: Change procedures / equipment / operating conditions | $100 | $375 |
$100
547
kWh
|
- | - | |
TOTAL RECOMMENDED | $72,441 | $400,015 |
$55,530
303,445
kWh
|
$8,754
-
kW-mo/yr
|
$8,157 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs