ITAC Assessment: MA0844
ITAC logo
ITAC Assessment: MA0844
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Metal finishing, powder coating, anodizing and plating
NAICS 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring
SIC 3479: Coating, Engraving, and Allied Services, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 54
Plant Area 120,000
ft2
Annual Production 15,000
units
Production Hrs. Annual 2,210
hrs
Location (State) Rhode Island

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,916 794,400
kWh
Electricity Demand $68,127 5,339
kW-mo/yr
Electricity Fees $2,533 -
Natural Gas $109,478 11,283
MMBtu
Waste Disposal Costs
Water Usage $40,279 7,119
Tgal
Water Disposal $5,710 7,119
Tgal
TOTAL YEARLY COSTS $318,043
RECOMMENDED SAVINGS* $21,395 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,466

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
01 2.9114: Use solar heat to make electricty $9,380 $10,000 $1,359
11,748
kWh
$9,021
-
kW-mo/yr
- $(-1,000.0)
02 2.3212: Optimize plant power factor $5,525 $7,135 - $5,525
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,466 $23,175 $3,879
33,525
kWh
$587
-
kW-mo/yr
- -
04 2.2437: Recover waste heat from equipment $853 $4,200 - - $853
-
MMBtu
-
05 2.2511: Insulate bare equipment $597 $895 - - $597
-
MMBtu
-
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $574 $2,100 $574
4,961
kWh
- - -
TOTAL RECOMMENDED $21,395 $47,505 $5,812
50,234
kWh
$15,133
-
kW-mo/yr
$1,450
-
MMBtu
$(-1,000.0)
TOTAL IMPLEMENTED $4,466 $23,175 $3,879
33,525
kWh
$587
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs