ITAC Assessment: MA0832
ITAC logo
ITAC Assessment: MA0832
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Clean water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $1
M
to 5
M
# of Employees 3
Plant Area 5,400
ft2
Annual Production 2,000,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $135,090 1,400,440
kWh
Electricity Demand $182,056 7,509
kW-mo/yr
Electricity Fees $3,000 -
Fuel Oil #2 $3,728 337
MMBtu
TOTAL YEARLY COSTS $323,874
RECOMMENDED SAVINGS* $8,496 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,091

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings
01 3.1191: Change procedures / equipment / operating conditions $2,405 $900 $2,405
25,055
kWh
- -
02 2.7234: Use heat pump for space conditioning $3,806 $2,150 $2,933
30,556
kWh
$873
-
kW-mo/yr
-
03 2.7234: Use heat pump for space conditioning $1,101 $12,675 $(-1,900.0)
(-19,787)
kWh
$(-727.0)
-
kW-mo/yr
$3,728
-
MMBtu
04 2.7221: Lower temperature during the winter season and vice-versa $1,184 $600 - - $1,184
-
MMBtu
TOTAL RECOMMENDED $8,496 $16,325 $3,438
35,824
kWh
$146
-
kW-mo/yr
$4,912
-
MMBtu
TOTAL IMPLEMENTED $6,091 $15,425 $1,033
10,769
kWh
$146
-
kW-mo/yr
$4,912
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs