ITAC Assessment: MA0818
ITAC logo
ITAC Assessment: MA0818
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Marine generators
NAICS 333618: Other Engine Equipment Manufacturing
SIC 3519: Internal Combustion Engines, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 63
Plant Area 113,000
ft2
Annual Production 1,650
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,353 563,850
kWh
Electricity Demand $53,311 3,605
kW-mo/yr
Electricity Fees $11,519 -
Natural Gas $50,325 5,491
MMBtu
Waste Disposal Costs
Water Usage $4,662 462
Tgal
Water Disposal $6,564 462
Tgal
TOTAL YEARLY COSTS $174,734
RECOMMENDED SAVINGS* $12,610 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,855

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.7221: Lower temperature during the winter season and vice-versa $4,422 $970 $344
3,996
kWh
- $4,078
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,320 $9,808 $1,930
22,439
kWh
$1,390
-
kW-mo/yr
- -
03 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle $1,714 $5,600 - - $1,714
-
MMBtu
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $837 $4,000 $837
9,728
kWh
- - -
05 3.4116: Meter recycled water (to reduce sewer charges) $789 $1,700 - - - $789
-
Tgal
06 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $782 $2,450 $168
1,959
kWh
- $614
-
MMBtu
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $746 $500 $746
8,680
kWh
- - -
TOTAL RECOMMENDED $12,610 $25,028 $4,025
46,802
kWh
$1,390
-
kW-mo/yr
$6,406
-
MMBtu
$789
-
Tgal
TOTAL IMPLEMENTED $4,855 $12,008 $2,676
31,119
kWh
$1,390
-
kW-mo/yr
- $789
-
Tgal
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs