Assessment Year | 2020 |
---|---|
Principal Product | Marine generators |
NAICS | 333618: Other Engine Equipment Manufacturing |
SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 63 |
Plant Area |
113,000
ft2
|
Annual Production | 1,650
pieces
|
Production Hrs. Annual | 2,210
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $48,353 | 563,850 |
kWh
|
$0.086 | |
Electricity Demand | $53,311 | 3,605 |
kW-mo/yr
|
$14.79 | |
Electricity Fees | $11,519 | - |
|
- | |
Natural Gas | $50,325 | 5,491 |
MMBtu
|
$9.16 | |
Waste Disposal Costs | |||||
Water Usage | $4,662 | 462 |
Tgal
|
$10.10 | |
Water Disposal | $6,564 | 462 |
Tgal
|
$14.22 | |
TOTAL YEARLY COSTS | $174,734 | ||||
RECOMMENDED SAVINGS* | $12,610 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $4,855 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $4,422 | $970 |
$344
3,996
kWh
|
- |
$4,078
-
MMBtu
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,320 | $9,808 |
$1,930
22,439
kWh
|
$1,390
-
kW-mo/yr
|
- | - | |
03 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $1,714 | $5,600 | - | - |
$1,714
-
MMBtu
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $837 | $4,000 |
$837
9,728
kWh
|
- | - | - | |
05 | 3.4116: Meter recycled water (to reduce sewer charges) | $789 | $1,700 | - | - | - |
$789
-
Tgal
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $782 | $2,450 |
$168
1,959
kWh
|
- |
$614
-
MMBtu
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $746 | $500 |
$746
8,680
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $12,610 | $25,028 |
$4,025
46,802
kWh
|
$1,390
-
kW-mo/yr
|
$6,406
-
MMBtu
|
$789
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,855 | $12,008 |
$2,676
31,119
kWh
|
$1,390
-
kW-mo/yr
|
- |
$789
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs