Assessment Year | 2020 |
---|---|
Principal Product | Plastic Injection Molded Products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 156 |
Plant Area |
90,292
ft2
|
Annual Production | 1,500,000
pieces
|
Production Hrs. Annual | 6,257
hrs
|
Location (State) | New Hampshire |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $411,572 | 3,582,000 |
kWh
|
$0.11 | |
Electricity Demand | $66,584 | 9,998 |
kW-mo/yr
|
$6.66 | |
Electricity Fees | $233 | - |
|
- | |
LPG | $138,019 | 10,291 |
MMBtu
|
$13.41 | |
Waste Disposal Costs | |||||
Water Usage | $3,667 | 337 |
Tgal
|
$10.88 | |
Water Disposal | $5,391 | 337 |
Tgal
|
$16.00 | |
TOTAL YEARLY COSTS | $625,466 | ||||
RECOMMENDED SAVINGS* | $183,185 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $19,339 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $89,868 | $533,354 |
$89,868
781,457
kWh
|
- | - | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $40,091 | $65,600 |
$3,785
32,909
kWh
|
- |
$36,306
-
MMBtu
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $33,887 | $69,625 |
$29,189
253,816
kWh
|
$4,698
-
kW-mo/yr
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,788 | $12,100 |
$9,788
85,117
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,694 | $12,100 |
$5,694
49,517
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,857 | $4,096 |
$3,484
30,292
kWh
|
$373
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $183,185 | $696,875 |
$141,808
1,233,108
kWh
|
$5,071
-
kW-mo/yr
|
$36,306
-
MMBtu
|
||
TOTAL IMPLEMENTED | $19,339 | $28,296 |
$18,966
164,926
kWh
|
$373
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs