Assessment Year | 2019 |
---|---|
Principal Product | Sewage water treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 22 |
Plant Area |
38,352
ft2
|
Annual Production | 2,738,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $282,897 | 2,493,360 |
kWh
|
$0.11 |
Electricity Demand | $28,863 | 9,124 |
kW-mo/yr
|
$3.16 |
Electricity Fees | $(-2,715.0) | - |
|
- |
Natural Gas | $37,260 | 4,604 |
MMBtu
|
$8.09 |
Fuel Oil #2 | $2,127 | 140 |
MMBtu
|
$15.19 |
TOTAL YEARLY COSTS | $348,432 | |||
RECOMMENDED SAVINGS* | $19,872 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,594 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,872 | $17,950 |
$5,167
45,728
kWh
|
$705
-
kW-mo/yr
|
|
02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,788 | $8,400 |
$4,310
38,146
kWh
|
$478
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,797 | $625 |
$3,797
33,603
kWh
|
- | |
04 | 2.4322: Use or replace with energy efficient substitutes | $3,310 | $51,675 |
$3,247
28,736
kWh
|
$63
-
kW-mo/yr
|
|
05 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $1,171 | $2,500 |
$1,171
10,361
kWh
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $934 | $2,484 |
$877
7,759
kWh
|
$57
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $19,872 | $83,634 |
$18,569
164,333
kWh
|
$1,303
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $11,594 | $28,834 |
$10,354
91,633
kWh
|
$1,240
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs