ITAC Assessment: MA0804
ITAC logo
ITAC Assessment: MA0804
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Surgical and medical instruments
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area 642,000
ft2
Annual Production 10,000
units
Production Hrs. Annual 3,120
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $497,889 3,772,949
kWh
Electricity Demand $205,885 28,887
kW-mo/yr
Electricity Fees $35,944 -
Natural Gas $311,713 49,826
MMBtu
TOTAL YEARLY COSTS $1,051,431
RECOMMENDED SAVINGS* $355,875 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $103,256

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.8114: Change rate schedules or other changes in utility service $227,379 $500 $(-26,277.0)
(-877,500)
kWh
$253,656
-
kW-mo/yr
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $100,108 $144,760 $87,778
664,987
kWh
$12,330
-
kW-mo/yr
- -
03 2.8121: Apply for tax-free status for energy purchases $25,240 $1,000 - - $25,240 -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,014 $300 $2,014
15,258
kWh
- - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $1,134 $1,000 - - - $1,134
-
MMBtu
TOTAL RECOMMENDED $355,875 $147,560 $63,515
(-197,255)
kWh
$265,986
-
kW-mo/yr
$25,240 $1,134
-
MMBtu
TOTAL IMPLEMENTED $103,256 $146,060 $89,792
680,245
kWh
$12,330
-
kW-mo/yr
- $1,134
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs