| Assessment Year | 2019 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS | 331524: Aluminum Foundries (except Die-Casting) |
| SIC | 3365: Aluminum Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 84 |
| Plant Area |
53,375
ft2
|
| Annual Production | 500
ton
|
| Production Hrs. Annual | 4,463
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $388,491 | 2,676,685 |
kWh
|
$0.15 |
| Electricity Demand | $71,159 | 12,354 |
kW-mo/yr
|
$5.76 |
| Electricity Fees | $5,767 | - |
|
- |
| Natural Gas | $105,443 | 11,286 |
MMBtu
|
$9.34 |
| TOTAL YEARLY COSTS | $570,860 | |||
| RECOMMENDED SAVINGS* | $68,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,935 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $27,506 | $138,640 |
$35,398
244,126
kWh
|
$6,843
-
kW-mo/yr
|
$(-9,735.0)
-
MMBtu
|
$(-5,000.0) | |
| 02 | 2.2414: Use waste heat from hot flue gases to preheat | $17,826 | $47,870 | - | - |
$17,826
-
MMBtu
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,442 | $14,461 |
$10,302
71,046
kWh
|
$1,140
-
kW-mo/yr
|
- | - | |
| 04 | 2.1113: Reduce combustion air flow to optimum | $5,709 | $2,500 | - | - |
$5,709
-
MMBtu
|
- | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,784 | $4,000 |
$4,784
32,990
kWh
|
- | - | - | |
| 06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,202 | $5,200 |
$1,398
9,640
kWh
|
- |
$(-196.0)
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $68,469 | $212,671 |
$51,882
357,802
kWh
|
$7,983
-
kW-mo/yr
|
$13,604
-
MMBtu
|
$(-5,000.0) | ||
| TOTAL IMPLEMENTED | $21,935 | $20,961 |
$15,086
104,036
kWh
|
$1,140
-
kW-mo/yr
|
$5,709
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs