ITAC Assessment: MA0793
ITAC logo
ITAC Assessment: MA0793
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2018
Principal Product Medical equipment
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3845: Electromedical and Electrotherapeutic Apparatus
Sales Range $100
M
to 500
M
# of Employees 700
Plant Area 513,000
ft2
Annual Production 270,000
units
Production Hrs. Annual 6,268
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,602,854 15,280,440
kWh
Electricity Demand $539,264 33,216
kW-mo/yr
Electricity Fees $(-57,762.0) -
Natural Gas $53,840 10,702
MMBtu
TOTAL YEARLY COSTS $2,138,196
RECOMMENDED SAVINGS* $54,147 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $9,594

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $34,323 $28,940 $34,323
326,884
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $8,582 $5,974 $6,634
63,181
kWh
$1,948
-
kW-mo/yr
-
03 2.7221: Lower temperature during the winter season and vice-versa $8,289 $5,525 $6,675
63,569
kWh
- $1,614
-
MMBtu
04 2.6218: Turn off equipment when not in use $1,522 $1,000 $1,522
14,492
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $1,012 $500 $1,012
9,634
kWh
- -
06 2.7314: Reduce ventilation air $419 $1,000 $39
371
kWh
- $380
-
MMBtu
TOTAL RECOMMENDED $54,147 $42,939 $50,205
478,131
kWh
$1,948
-
kW-mo/yr
$1,994
-
MMBtu
TOTAL IMPLEMENTED $9,594 $6,474 $7,646
72,815
kWh
$1,948
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs