Assessment Year | 2018 |
---|---|
Principal Product | Water treatment |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | $10 M to 50M |
# of Employees | 51 |
Plant Area |
100,000
ft2
|
Annual Production | 8,370,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,266,846 | 13,728,918 |
kWh
|
$0.092 |
Electricity Demand | $435,058 | 24,791 |
kW-mo/yr
|
$17.55 |
Electricity Fees | $26,400 | - |
|
- |
Natural Gas | $78,730 | 9,943 |
MMBtu
|
$7.92 |
TOTAL YEARLY COSTS | $1,807,034 | |||
RECOMMENDED SAVINGS* | $329,708 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $116,387 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3191: Use demand controller or load shedder | $207,219 | $1,000,000 | - |
$207,219
-
kW-mo/yr
|
- | |
02 | 3.1191: Change procedures / equipment / operating conditions | $48,698 | $124,000 |
$48,698
529,331
kWh
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,345 | $33,774 |
$12,254
133,197
kWh
|
$12,091
-
kW-mo/yr
|
- | |
04 | 3.1191: Change procedures / equipment / operating conditions | $19,380 | $500 |
$19,380
210,652
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,372 | $5,831 |
$8,058
87,588
kWh
|
- |
$7,314
-
MMBtu
|
|
06 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,658 | $25,350 |
$6,658
72,366
kWh
|
- | - | |
07 | 2.6218: Turn off equipment when not in use | $4,286 | $100 |
$3,286
35,716
kWh
|
$1,000
-
kW-mo/yr
|
- | |
08 | 2.4322: Use or replace with energy efficient substitutes | $1,934 | $6,774 |
$1,934
21,024
kWh
|
- | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,816 | $4,785 |
$1,816
19,736
kWh
|
- | - | |
TOTAL RECOMMENDED | $329,708 | $1,201,114 |
$102,084
1,109,610
kWh
|
$220,310
-
kW-mo/yr
|
$7,314
-
MMBtu
|
||
TOTAL IMPLEMENTED | $116,387 | $196,229 |
$96,982
1,054,158
kWh
|
$12,091
-
kW-mo/yr
|
$7,314
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs