ITAC Assessment: MA0785
ITAC logo
ITAC Assessment: MA0785
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2017
Principal Product Asphalt paving mixtures and block
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range $10
M
to 50
M
# of Employees 6
Plant Area 50,000
ft2
Annual Production 265,000
ton
Production Hrs. Annual 2,808
hrs
Location (State) Massachusetts

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,723 771,368
kWh
Electricity Demand $49,826 3,650
kW-mo/yr
Electricity Fees $8,400 -
Natural Gas $359,317 58,446
MMBtu
TOTAL YEARLY COSTS $477,266
RECOMMENDED SAVINGS* $10,071 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,907

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,893 $20,000 $6,893
89,520
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,469 $2,569 $928
12,051
kWh
$541
-
kW-mo/yr
-
03 2.1232: Keep boiler tubes clean $1,014 $1,200 - - $1,014
-
MMBtu
04 2.2511: Insulate bare equipment $695 $959 - - $695
-
MMBtu
TOTAL RECOMMENDED $10,071 $24,728 $7,821
101,571
kWh
$541
-
kW-mo/yr
$1,709
-
MMBtu
TOTAL IMPLEMENTED $7,907 $21,200 $6,893
89,520
kWh
- $1,014
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs