Assessment Year | 2017 |
---|---|
Principal Product | Asphalt paving mixtures and block |
NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 6 |
Plant Area |
50,000
ft2
|
Annual Production | 265,000
ton
|
Production Hrs. Annual | 2,808
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $59,723 | 771,368 |
kWh
|
$0.077 |
Electricity Demand | $49,826 | 3,650 |
kW-mo/yr
|
$13.65 |
Electricity Fees | $8,400 | - |
|
- |
Natural Gas | $359,317 | 58,446 |
MMBtu
|
$6.15 |
TOTAL YEARLY COSTS | $477,266 | |||
RECOMMENDED SAVINGS* | $10,071 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,907 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,893 | $20,000 |
$6,893
89,520
kWh
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,469 | $2,569 |
$928
12,051
kWh
|
$541
-
kW-mo/yr
|
- | |
03 | 2.1232: Keep boiler tubes clean | $1,014 | $1,200 | - | - |
$1,014
-
MMBtu
|
|
04 | 2.2511: Insulate bare equipment | $695 | $959 | - | - |
$695
-
MMBtu
|
|
TOTAL RECOMMENDED | $10,071 | $24,728 |
$7,821
101,571
kWh
|
$541
-
kW-mo/yr
|
$1,709
-
MMBtu
|
||
TOTAL IMPLEMENTED | $7,907 | $21,200 |
$6,893
89,520
kWh
|
- |
$1,014
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs