Assessment Year | 2017 |
---|---|
Principal Product | metal nozzles |
NAICS | 332999: All Other Miscellaneous Fabricated Metal Product Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
60,000
ft2
|
Annual Production | 24,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $179,440 | 1,452,733 |
kWh
|
$0.12 |
Electricity Demand | $60,299 | 4,577 |
kW-mo/yr
|
$13.17 |
Electricity Fees | $8,766 | - |
|
- |
LPG | $103,573 | 7,028 |
MMBtu
|
$14.74 |
TOTAL YEARLY COSTS | $352,078 | |||
RECOMMENDED SAVINGS* | $34,391 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,673 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | LPG Savings |
---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $16,653 | $30,000 | - |
$16,653
-
MMBtu
|
|
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,580 | $14,050 |
$8,580
69,196
kWh
|
- | |
03 | 2.7313: Recycle air for heating, ventilation and air conditioning | $5,593 | $10,625 |
$(-6,167.0)
(-49,761)
kWh
|
$11,760
-
MMBtu
|
|
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,564 | $6,660 |
$1,564
12,611
kWh
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,500 | $1,000 |
$1,500
12,098
kWh
|
- | |
06 | 2.1122: Re-size charging openings or add a movable door on equipment | $501 | $100 | - |
$501
-
MMBtu
|
|
TOTAL RECOMMENDED | $34,391 | $62,435 |
$5,477
44,144
kWh
|
$28,914
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,673 | $25,675 |
$3,913
31,533
kWh
|
$11,760
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs