Assessment Year | 2017 |
---|---|
Principal Product | Powdered metal products |
NAICS | 332117: Powder Metallurgy Part Manufacturing |
SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 225 |
Plant Area |
88,000
ft2
|
Annual Production | 4,200,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,329,652 | 12,250,500 |
kWh
|
$0.11 |
Electricity Demand | $86,859 | 22,158 |
kW-mo/yr
|
$3.92 |
Electricity Fees | $2,400 | - |
|
- |
Natural Gas | $52,752 | 4,901 |
MMBtu
|
$10.76 |
TOTAL YEARLY COSTS | $1,471,663 | |||
RECOMMENDED SAVINGS* | $146,303 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $90,487 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $90,487 | $39,330 |
$90,487
830,155
kWh
|
- | - | |
02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $30,931 | $24,720 |
$45,678
419,067
kWh
|
$4,481
-
kW-mo/yr
|
$(-19,228.0)
-
MMBtu
|
|
03 | 2.2511: Insulate bare equipment | $12,391 | $11,273 |
$12,391
113,638
kWh
|
- | - | |
04 | 2.3311: Replace dc equipment with ac equipment | $8,620 | $57,572 |
$8,620
79,080
kWh
|
- | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,874 | $7,200 |
$3,874
35,539
kWh
|
- | - | |
TOTAL RECOMMENDED | $146,303 | $140,095 |
$161,050
1,477,479
kWh
|
$4,481
-
kW-mo/yr
|
$(-19,228.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $90,487 | $39,330 |
$90,487
830,155
kWh
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs