| Assessment Year | 2016 |
|---|---|
| Principal Product | Rubber Coated Fabrics and Clothing |
| NAICS | 313320: Fabric Coating Mills |
| SIC | 3069: Fabricated Rubber Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 14 |
| Plant Area |
88,000
ft2
|
| Annual Production | 4,500
thousand feet
|
| Production Hrs. Annual | 2,040
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $45,119 | 270,866 |
kWh
|
$0.17 | |
| Electricity Demand | $15,997 | 2,717 |
kW-mo/yr
|
$5.89 | |
| Electricity Fees | $462 | - |
|
- | |
| Natural Gas | $37,797 | 4,023 |
MMBtu
|
$9.40 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,430 | 21,090 |
Tgal
|
$0.068 | |
| TOTAL YEARLY COSTS | $100,805 | ||||
| RECOMMENDED SAVINGS* | $7,924 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $3,086 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,870 | $3,830 |
$3,870
23,171
kWh
|
- | - | - | |
| 02 | 2.2136: Install / repair insulation on steam lines | $939 | $3,914 | - | - |
$939
-
MMBtu
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $871 | $1,000 |
$871
5,218
kWh
|
- | - | - | |
| 04 | 3.4151: Minimize water usage | $587 | $3,650 |
$(-41.0)
(-248)
kWh
|
- | - |
$628
-
Tgal
|
|
| 05 | 2.3212: Optimize plant power factor | $515 | $3,480 | - |
$515
-
kW-mo/yr
|
- | - | |
| 06 | 2.2153: Close off unneeded steam lines | $376 | $4,348 | - | - |
$376
-
MMBtu
|
- | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $331 | $2,648 |
$331
1,983
kWh
|
- | - | - | |
| 08 | 2.2136: Install / repair insulation on steam lines | $313 | $1,944 | - | - |
$313
-
MMBtu
|
- | |
| 09 | 2.2625: Chill water to the highest temperature possible | $122 | $300 |
$122
728
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $7,924 | $25,114 |
$5,153
30,852
kWh
|
$515
-
kW-mo/yr
|
$1,628
-
MMBtu
|
$628
-
Tgal
|
||
| TOTAL IMPLEMENTED | $3,086 | $14,856 |
$830
4,970
kWh
|
- |
$1,628
-
MMBtu
|
$628
-
Tgal
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Usage Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs