ITAC Assessment: MA0748
ITAC logo
ITAC Assessment: MA0748
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Insulated wire
NAICS 332618: Other Fabricated Wire Product Manufacturing
SIC 3357: Drawing and Insulating of Nonferrous Wire
Sales Range $50
M
to 100
M
# of Employees 104
Plant Area 73,563
ft2
Annual Production 24,000
thousand feet
Production Hrs. Annual 6,864
hrs
Location (State) Vermont

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $299,403 3,242,047
kWh
Electricity Demand $126,088 14,762
kW-mo/yr
Electricity Fees $1,411 -
Natural Gas $69,655 8,512
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $54,918 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,713

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.2511: Insulate bare equipment $35,959 $11,580 $35,959
390,862
kWh
-
02 2.2414: Use waste heat from hot flue gases to preheat $9,716 $9,850 - $9,716
-
MMBtu
03 2.2437: Recover waste heat from equipment $4,530 $9,000 - $4,530
-
MMBtu
04 2.7135: Install occupancy sensors $1,687 $5,365 $1,687
18,334
kWh
-
05 2.6218: Turn off equipment when not in use $1,137 $100 $1,137
12,355
kWh
-
06 2.7221: Lower temperature during the winter season and vice-versa $1,168 $500 - $1,168
-
MMBtu
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $721 $2,245 $721
7,833
kWh
-
TOTAL RECOMMENDED $54,918 $38,640 $39,504
429,384
kWh
$15,414
-
MMBtu
TOTAL IMPLEMENTED $4,713 $8,210 $3,545
38,522
kWh
$1,168
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs