ITAC Assessment: MA0745
ITAC logo
ITAC Assessment: MA0745
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product Fabricated metal parts
NAICS 332322: Sheet Metal Work Manufacturing
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 67
Plant Area 18,000
ft2
Annual Production 1,700,000
lb
Production Hrs. Annual 4,394
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,114 585,987
kWh
Electricity Demand $30,434 2,167
kW-mo/yr
Electricity Fees $388 -
Fuel Oil #2 $20,205 764
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,155 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $2,455

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,700 $3,600 $3,700
34,903
kWh
02 2.7135: Install occupancy sensors $1,433 $1,224 $1,433
13,518
kWh
03 2.7232: Replace existing hvac unit with high efficiency model $1,022 $36,150 $1,022
9,642
kWh
TOTAL RECOMMENDED $6,155 $40,974 $6,155
58,063
kWh
TOTAL IMPLEMENTED $2,455 $37,374 $2,455
23,160
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs