Assessment Year | 2015 |
---|---|
Principal Product | Gates, valves & water control equipment |
NAICS | 332911: Industrial Valve Manufacturing |
SIC | 3491: Industrial Valves |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
245,668
ft2
|
Annual Production | 1,500
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $773,160 | 6,902,600 |
kWh
|
$0.11 |
Electricity Demand | $68,553 | 17,302 |
kW-mo/yr
|
$3.96 |
Electricity Fees | $19,144 | - |
|
- |
LPG | $374,692 | 19,271 |
MMBtu
|
$19.44 |
Fuel Oil #6 | $347,826 | 18,595 |
MMBtu
|
$18.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $95,372 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $71,037 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $59,139 | $500 | - | - | $59,139 | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $11,551 | $1,000 |
$4,181
37,331
kWh
|
$7,370
-
MMBtu
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,739 | $11,430 |
$9,739
86,956
kWh
|
- | - | |
04 | 2.7221: Lower temperature during the winter season and vice-versa | $5,924 | $3,000 |
$1,227
10,951
kWh
|
$4,697
-
MMBtu
|
- | |
05 | 2.2437: Recover waste heat from equipment | $4,433 | $8,441 | - |
$4,433
-
MMBtu
|
- | |
06 | 2.2511: Insulate bare equipment | $4,239 | $2,000 | - |
$4,239
-
MMBtu
|
- | |
07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $347 | $400 |
$347
3,095
kWh
|
- | - | |
TOTAL RECOMMENDED | $95,372 | $26,771 |
$15,494
138,333
kWh
|
$20,739
-
MMBtu
|
$59,139 | ||
TOTAL IMPLEMENTED | $71,037 | $1,900 |
$4,528
40,426
kWh
|
$7,370
-
MMBtu
|
$59,139 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Fuel Oil #6 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs