ITAC Assessment: MA0727
ITAC logo
ITAC Assessment: MA0727
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product tissue paper
NAICS 322121: Paper (except Newsprint) Mills
SIC 2621: Paper Mills
Sales Range $50
M
to 100
M
# of Employees 180
Plant Area 500,000
ft2
Annual Production 126,000
ton
Production Hrs. Annual 8,568
hrs
Location (State) New Hampshire

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,990,454 118,325,670
kWh
Electricity Demand $339,083 45,808
kW-mo/yr
Electricity Fees $12,692 -
Natural Gas $7,040,099 1,113,195
MMBtu
Other Gas $403,605 108,827
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,141 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,603

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $82,693 $153,000 $82,693
1,252,928
kWh
- -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $52,084 $127,730 $52,084
789,155
kWh
- -
03 2.8123: Pay utility bills on time $6,481 $500 - - $6,481
04 2.2136: Install / repair insulation on steam lines $2,761 $1,598 - $2,761
-
MMBtu
-
05 2.4131: Size electric motors for peak operating efficiency $1,122 $1,500 $1,122
9,593
kWh
- -
TOTAL RECOMMENDED $145,141 $284,328 $135,899
2,051,676
kWh
$2,761
-
MMBtu
$6,481
TOTAL IMPLEMENTED $7,603 $2,000 $1,122
9,593
kWh
- $6,481
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs