Assessment Year | 2014 |
---|---|
Principal Product | Drinking water |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 4941: Water Supply |
Sales Range | $10 M to 50M |
# of Employees | 6 |
Plant Area |
74,000
ft2
|
Annual Production | 5,456,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $237,081 | 3,497,760 |
kWh
|
$0.068 |
Electricity Demand | $93,194 | 6,101 |
kW-mo/yr
|
$15.28 |
Electricity Fees | $949 | - |
|
- |
Fuel Oil #2 | $106,420 | 3,787 |
MMBtu
|
$28.10 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $35,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $12,296 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.3137: Use power during off-peak periods | $11,298 | $500 | - |
$10,616
-
kW-mo/yr
|
- | $682 | |
02 | 2.4131: Size electric motors for peak operating efficiency | $10,940 | $1,500 |
$10,940
161,357
kWh
|
- | - | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $3,147 | $9,900 | - | - |
$3,147
-
MMBtu
|
- | |
04 | 2.7314: Reduce ventilation air | $2,443 | $3,000 |
$55
816
kWh
|
- |
$2,388
-
MMBtu
|
- | |
05 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $1,818 | $2,750 |
$160
2,369
kWh
|
- |
$1,658
-
MMBtu
|
- | |
06 | 2.2136: Install / repair insulation on steam lines | $1,742 | $1,450 | - | - |
$1,742
-
MMBtu
|
- | |
07 | 2.7314: Reduce ventilation air | $1,630 | $3,750 | - | - |
$1,630
-
MMBtu
|
- | |
08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $998 | $200 |
$998
14,717
kWh
|
- | - | - | |
09 | 2.8123: Pay utility bills on time | $949 | $500 | - | - | - | $949 | |
10 | 2.7135: Install occupancy sensors | $599 | $1,600 |
$599
8,830
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $35,564 | $25,150 |
$12,752
188,089
kWh
|
$10,616
-
kW-mo/yr
|
$10,565
-
MMBtu
|
$1,631 | ||
TOTAL IMPLEMENTED | $12,296 | $700 |
$998
14,717
kWh
|
$10,616
-
kW-mo/yr
|
- | $682 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs