Assessment Year | 2013 |
---|---|
Principal Product | Rpair of Helicopter Parts |
NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 200 |
Plant Area |
180,000
ft2
|
Annual Production | 4,560
pieces
|
Production Hrs. Annual | 5,406
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $333,834 | 2,764,400 |
kWh
|
$0.12 |
Electricity Demand | $102,784 | 7,380 |
kW-mo/yr
|
$13.93 |
Electricity Fees | $4,116 | - |
|
- |
Natural Gas | $88,481 | 6,104 |
MMBtu
|
$14.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $49,273 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $30,225 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $15,477 | $1,400 | - | - | $15,477 | |
02 | 2.7224: Reduce space conditioning during non-working hours | $10,906 | $7,500 |
$6,773
56,918
kWh
|
$4,133
-
MMBtu
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $7,493 | $11,000 |
$7,493
60,916
kWh
|
- | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $4,864 | $200 | - | - | $4,864 | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $2,474 | $200 |
$1,143
9,603
kWh
|
$1,331
-
MMBtu
|
- | |
06 | 2.2135: Repair and eliminate steam leaks | $2,358 | $1,120 |
$2,358
19,167
kWh
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,130 | $1,020 |
$2,130
17,313
kWh
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,106 | $6,390 |
$2,106
17,118
kWh
|
- | - | |
09 | 2.2136: Install / repair insulation on steam lines | $1,465 | $1,650 | - |
$1,465
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $49,273 | $30,480 |
$22,003
181,035
kWh
|
$6,929
-
MMBtu
|
$20,341 | ||
TOTAL IMPLEMENTED | $30,225 | $21,040 |
$19,897
163,917
kWh
|
$5,464
-
MMBtu
|
$4,864 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs