Assessment Year | 2013 |
---|---|
Principal Product | Semiconductor industry capital equipment |
NAICS | 333242: Semiconductor Machinery Manufacturing |
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 19 |
Plant Area |
32,000
ft2
|
Annual Production | 15
pieces
|
Production Hrs. Annual | 3,380
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,793 | 894,800 |
kWh
|
$0.098 |
Electricity Demand | $9,927 | 2,456 |
kW-mo/yr
|
$4.04 |
Electricity Fees | $2,370 | - |
|
- |
Natural Gas | $137 | 16 |
MMBtu
|
$8.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,243 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,997 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $14,613 | $1,000 |
$18,837
190,084
kWh
|
$1,090
-
kW-mo/yr
|
$(-5,314.0)
-
MMBtu
|
|
02 | 2.6218: Turn off equipment when not in use | $972 | $200 |
$972
9,804
kWh
|
- | - | |
03 | 2.7135: Install occupancy sensors | $807 | $1,840 |
$807
8,145
kWh
|
- | - | |
04 | 2.3212: Optimize plant power factor | $439 | $3,057 | - |
$439
-
kW-mo/yr
|
- | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $412 | $200 |
$412
4,157
kWh
|
- | - | |
TOTAL RECOMMENDED | $17,243 | $6,297 |
$21,028
212,190
kWh
|
$1,529
-
kW-mo/yr
|
$(-5,314.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,997 | $1,400 |
$20,221
204,045
kWh
|
$1,090
-
kW-mo/yr
|
$(-5,314.0)
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs