Assessment Year | 2012 |
---|---|
Principal Product | Adhesives |
NAICS | 325520: Adhesive Manufacturing |
SIC | 2891: Adhesives and Sealants |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
100,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 4,030
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $175,837 | 1,836,000 |
kWh
|
$0.096 |
Electricity Demand | $44,928 | 4,992 |
kW-mo/yr
|
$9.00 |
Electricity Fees | $120 | - |
|
- |
Natural Gas | $271,688 | 21,516 |
MMBtu
|
$12.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,337 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $22,622 | $21,500 |
$11,345
119,930
kWh
|
$11,277
-
MMBtu
|
|
02 | 2.2136: Install / repair insulation on steam lines | $10,004 | $9,352 | - |
$10,004
-
MMBtu
|
|
03 | 2.7243: Improve air circulation with destratification fans / other methods | $2,644 | $2,250 |
$(-228.0)
(-2,409)
kWh
|
$2,872
-
MMBtu
|
|
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,988 | $1,800 |
$1,988
21,024
kWh
|
- | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $1,762 | $15,050 |
$1,762
18,636
kWh
|
- | |
06 | 2.7135: Install occupancy sensors | $1,689 | $4,605 |
$1,689
17,853
kWh
|
- | |
TOTAL RECOMMENDED | $40,709 | $54,557 |
$16,556
175,034
kWh
|
$24,153
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,337 | $16,207 |
$1,461
15,444
kWh
|
$12,876
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs