Assessment Year | 2011 |
---|---|
Principal Product | Extruded and coated film |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 105 |
Plant Area |
85,000
ft2
|
Annual Production | 4,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $414,819 | 4,085,550 |
kWh
|
$0.10 |
Electricity Demand | $46,565 | 11,879 |
kW-mo/yr
|
$3.92 |
Electricity Fees | $2,400 | - |
|
- |
Natural Gas | $138,902 | 16,919 |
MMBtu
|
$8.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,393 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,714 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.1113: Reduce combustion air flow to optimum | $24,679 | $50,000 | - |
$24,679
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,021 | $2,800 |
$12,021
118,441
kWh
|
- | |
03 | 2.7224: Reduce space conditioning during non-working hours | $1,273 | $200 | - |
$1,273
-
MMBtu
|
|
04 | 2.7311: Ventilation system to shut off when room is not in use | $1,113 | $200 |
$809
7,978
kWh
|
$304
-
MMBtu
|
|
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $821 | $200 |
$821
8,093
kWh
|
- | |
06 | 2.7124: Make a practice of turning off lights when not needed | $486 | $100 |
$486
4,792
kWh
|
- | |
TOTAL RECOMMENDED | $40,393 | $53,500 |
$14,137
139,304
kWh
|
$26,256
-
MMBtu
|
||
TOTAL IMPLEMENTED | $15,714 | $3,500 |
$14,137
139,304
kWh
|
$1,577
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs