Assessment Year | 2010 |
---|---|
Principal Product | Plastic moldings |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
53,000
ft2
|
Annual Production | 120,000,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $209,238 | 2,175,360 |
kWh
|
$0.096 |
Electricity Demand | $34,442 | 6,026 |
kW-mo/yr
|
$5.72 |
Electricity Fees | $38,937 | - |
|
- |
Natural Gas | $12,248 | 884 |
MMBtu
|
$13.86 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $110,381 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $72,952 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.2622: Replace existing chiller with high efficiency model | $35,538 | $103,290 |
$35,538
358,972
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $35,141 | $119,100 |
$31,626
319,457
kWh
|
$3,515
-
kW-mo/yr
|
|
03 | 2.2691: Shut off cooling if cold outside air will cool process | $20,648 | $35,545 |
$20,648
208,648
kWh
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,781 | $7,735 |
$16,781
169,504
kWh
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,273 | $1,800 |
$2,273
22,958
kWh
|
- | |
TOTAL RECOMMENDED | $110,381 | $267,470 |
$106,866
1,079,539
kWh
|
$3,515
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $72,952 | $224,190 |
$69,437
701,387
kWh
|
$3,515
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs