| Assessment Year | 2010 |
|---|---|
| Principal Product | Aerospace components |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
110,000
ft2
|
| Annual Production | 3,000
pieces
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | Connecticut |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $435,538 | 3,282,707 |
kWh
|
$0.13 |
| Electricity Demand | $134,920 | 13,770 |
kW-mo/yr
|
$9.80 |
| Electricity Fees | $9,828 | - |
|
- |
| Fuel Oil #4 | $178,067 | 12,365 |
MMBtu
|
$14.40 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $181,361 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $129,619 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $33,238 | $900 |
$33,238
231,782
kWh
|
- | - | - | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $32,273 | $19,075 |
$27,685
193,065
kWh
|
$4,588
-
kW-mo/yr
|
- | - | |
| 03 | 2.2136: Install / repair insulation on steam lines | $2,578 | $2,400 | - | - | - |
$2,578
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $16,891 | $15,755 | - | - | - |
$16,891
-
MMBtu
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $3,718 | $3,915 |
$3,718
25,925
kWh
|
- | - | - | |
| 06 | 2.4226: Use / purchase optimum sized compressor | $36,936 | $68,200 |
$36,936
257,573
kWh
|
- | - | - | |
| 07 | 2.1331: Burn a less expensive grade of fuel | $54,013 | $100,000 | - | - |
$(-124,045.0)
-
MMBtu
|
$178,058
-
MMBtu
|
|
| 08 | 2.7135: Install occupancy sensors | $1,714 | $3,865 |
$1,714
11,950
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $181,361 | $214,110 |
$103,291
720,295
kWh
|
$4,588
-
kW-mo/yr
|
$(-124,045.0)
-
MMBtu
|
$197,527
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $129,619 | $176,880 |
$75,606
527,230
kWh
|
- |
$(-124,045.0)
-
MMBtu
|
$178,058
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #4 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs