Assessment Year | 2009 |
---|---|
Principal Product | Electrical fittings |
NAICS | 332216: Saw Blade and Handtool Manufacturing |
SIC | 3644: Noncurrent-Carrying Wiring Devices |
Sales Range | $50 M to 100M |
# of Employees | 207 |
Plant Area |
140,000
ft2
|
Annual Production | 3,000
ton
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $731,218 | 5,222,988 |
kWh
|
$0.14 |
Electricity Demand | $105,398 | 23,466 |
kW-mo/yr
|
$4.49 |
Electricity Fees | $2,976 | - |
|
- |
Natural Gas | $504,864 | 36,757 |
MMBtu
|
$13.74 |
Fuel Oil #2 | $40,024 | 3,480 |
MMBtu
|
$11.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,873 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $21,420 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $18,774 | $1,000 |
$5,424
40,030
kWh
|
- |
$13,350
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,340 | $96,800 |
$11,340
83,689
kWh
|
- | - | |
03 | 2.1224: Replace boiler | $10,080 | $30,700 | - | - |
$10,080
-
MMBtu
|
|
04 | 2.2514: Cover open tanks | $10,013 | $5,866 | - | - |
$10,013
-
MMBtu
|
|
05 | 2.2511: Insulate bare equipment | $2,941 | $3,219 | - | - |
$2,941
-
MMBtu
|
|
06 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,725 | $18,300 |
$2,885
21,294
kWh
|
$670
-
kW-mo/yr
|
$1,170
-
MMBtu
|
|
TOTAL RECOMMENDED | $57,873 | $155,885 |
$19,649
145,013
kWh
|
$670
-
kW-mo/yr
|
$37,554
-
MMBtu
|
||
TOTAL IMPLEMENTED | $21,420 | $127,500 |
$11,340
83,689
kWh
|
- |
$10,080
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs