ITAC Assessment: MA0651
ITAC logo
ITAC Assessment: MA0651
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Electrical fittings
NAICS 332216: Saw Blade and Handtool Manufacturing
SIC 3644: Noncurrent-Carrying Wiring Devices
Sales Range $50
M
to 100
M
# of Employees 207
Plant Area 140,000
ft2
Annual Production 3,000
ton
Production Hrs. Annual 4,160
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $731,218 5,222,988
kWh
Electricity Demand $105,398 23,466
kW-mo/yr
Electricity Fees $2,976 -
Natural Gas $504,864 36,757
MMBtu
Fuel Oil #2 $40,024 3,480
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,873 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,420

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7314: Reduce ventilation air $18,774 $1,000 $5,424
40,030
kWh
- $13,350
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $11,340 $96,800 $11,340
83,689
kWh
- -
03 2.1224: Replace boiler $10,080 $30,700 - - $10,080
-
MMBtu
04 2.2514: Cover open tanks $10,013 $5,866 - - $10,013
-
MMBtu
05 2.2511: Insulate bare equipment $2,941 $3,219 - - $2,941
-
MMBtu
06 2.1311: Replace electrically-operated equipment with fossil fuel equipment $4,725 $18,300 $2,885
21,294
kWh
$670
-
kW-mo/yr
$1,170
-
MMBtu
TOTAL RECOMMENDED $57,873 $155,885 $19,649
145,013
kWh
$670
-
kW-mo/yr
$37,554
-
MMBtu
TOTAL IMPLEMENTED $21,420 $127,500 $11,340
83,689
kWh
- $10,080
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs