| Assessment Year | 2008 |
|---|---|
| Principal Product | Paper mill roll covers |
| NAICS | 322121: Paper (except Newsprint) Mills |
| SIC | 2621: Paper Mills |
| Sales Range | $10 M to 50M |
| # of Employees | 25 |
| Plant Area |
50,000
ft2
|
| Annual Production | 500
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | New Hampshire |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $140,318 | 1,263,600 |
kWh
|
$0.11 |
| Electricity Demand | $40,090 | 5,053 |
kW-mo/yr
|
$7.93 |
| Electricity Fees | $1,308 | - |
|
- |
| Natural Gas | $108,397 | 9,026 |
MMBtu
|
$12.01 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $24,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,530 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,279 | $27,924 |
$10,996
99,770
kWh
|
$2,283
-
kW-mo/yr
|
- | |
| 02 | 2.2437: Recover waste heat from equipment | $4,095 | $4,354 | - | - |
$4,095
-
MMBtu
|
|
| 03 | 2.7314: Reduce ventilation air | $3,315 | $1,000 | - | - |
$3,315
-
MMBtu
|
|
| 04 | 2.3212: Optimize plant power factor | $1,935 | $6,500 | - |
$1,935
-
kW-mo/yr
|
- | |
| 05 | 2.1213: Direct warmest air to combustion intake | $1,273 | $5,500 | - | - |
$1,273
-
MMBtu
|
|
| 06 | 2.3212: Optimize plant power factor | $391 | $900 |
$391
3,554
kWh
|
- | - | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $251 | $120 |
$251
2,279
kWh
|
- | - | |
| TOTAL RECOMMENDED | $24,539 | $46,298 |
$11,638
105,603
kWh
|
$4,218
-
kW-mo/yr
|
$8,683
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,530 | $28,044 |
$11,247
102,049
kWh
|
$2,283
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs