| Assessment Year | 2008 |
|---|---|
| Principal Product | FLocked substrates |
| NAICS | 313230: Nonwoven Fabric Mills |
| SIC | 2297: Non-woven Fabrics |
| Sales Range | $10 M to 50M |
| # of Employees | 48 |
| Plant Area |
113,000
ft2
|
| Annual Production | 105,000
thousand feet
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Massachusetts |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $276,187 | 2,906,400 |
kWh
|
$0.095 |
| Electricity Demand | $47,142 | 10,272 |
kW-mo/yr
|
$4.59 |
| Electricity Fees | $840 | - |
|
- |
| Natural Gas | $652,214 | 52,446 |
MMBtu
|
$12.44 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $287,087 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $3,028 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2444: Use hot process fluids to preheat incoming process fluids | $280,575 | $3,040,000 |
$(-17,718.0)
(-186,500)
kWh
|
$(-2,046.0)
-
kW-mo/yr
|
$300,339
-
MMBtu
|
|
| 02 | 2.1392: Replace purchased steam with other energy source | $3,484 | $3,300 | - | - |
$3,484
-
MMBtu
|
|
| 03 | 2.2136: Install / repair insulation on steam lines | $3,028 | $3,000 | - | - |
$3,028
-
MMBtu
|
|
| TOTAL RECOMMENDED | $287,087 | $3,046,300 |
$(-17,718.0)
(-186,500)
kWh
|
$(-2,046.0)
-
kW-mo/yr
|
$306,851
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $3,028 | $3,000 | - | - |
$3,028
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs