Assessment Year | 2008 |
---|---|
Principal Product | Cold rolled and drawn metal parts |
NAICS | 331221: Rolled Steel Shape Manufacturing |
SIC | 3316: Cold-Rolled Steel Sheet, Strip, and Bars |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
99,920
ft2
|
Annual Production | 14,100,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $296,411 | 2,227,200 |
kWh
|
$0.13 |
Electricity Demand | $31,737 | 6,832 |
kW-mo/yr
|
$4.65 |
LPG | $21,533 | 1,577 |
MMBtu
|
$13.65 |
Fuel Oil #2 | $239,517 | 18,089 |
MMBtu
|
$13.24 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $132,689 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $99,524 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2212: Use minimum safe oven ventilation | $17,227 | $51,900 | - | - | - |
$17,227
-
MMBtu
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $21,508 | $40,166 |
$19,930
170,344
kWh
|
$1,578
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7314: Reduce ventilation air | $21,303 | $8,200 | - | - | - | - |
$21,303
-
MMBtu
|
- | |
04 | 3.4114: Replace city water with recycled water via cooling tower | $18,922 | $4,000 | - | - | - | - | - |
$18,922
-
Tgal
|
|
05 | 2.1331: Burn a less expensive grade of fuel | $16,990 | $27,590 | - | - |
$(-244,040.0)
-
MMBtu
|
$21,530
-
MMBtu
|
$239,500
-
MMBtu
|
- | |
06 | 2.2514: Cover open tanks | $13,756 | $53,000 | - | - | - | - |
$13,756
-
MMBtu
|
- | |
07 | 2.2136: Install / repair insulation on steam lines | $10,446 | $3,288 | - | - | - | - |
$10,446
-
MMBtu
|
- | |
08 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $4,508 | $12,000 | - | - | - | - |
$4,508
-
MMBtu
|
- | |
09 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,255 | $5,700 |
$3,255
28,557
kWh
|
- | - | - | - | - | |
10 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $2,859 | $1,200 |
$4,380
37,440
kWh
|
$663
-
kW-mo/yr
|
- |
$(-2,184.0)
-
MMBtu
|
- | - | |
11 | 2.4221: Install compressor air intakes in coolest locations | $1,035 | $1,600 |
$1,035
8,845
kWh
|
- | - | - | - | - | |
12 | 2.2212: Use minimum safe oven ventilation | $880 | $500 |
$880
7,527
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $132,689 | $209,144 |
$29,480
252,713
kWh
|
$2,241
-
kW-mo/yr
|
$(-244,040.0)
-
MMBtu
|
$36,573
-
MMBtu
|
$289,513
-
MMBtu
|
$18,922
-
Tgal
|
||
TOTAL IMPLEMENTED | $99,524 | $148,478 |
$880
7,527
kWh
|
- |
$(-244,040.0)
-
MMBtu
|
$38,757
-
MMBtu
|
$285,005
-
MMBtu
|
$18,922
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | LPG Savings | Fuel Oil #2 Savings | Water Disposal Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs