Assessment Year | 2008 |
---|---|
Principal Product | Specialty papers |
NAICS | 322299: All Other Converted Paper Product Manufacturing |
SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 49 |
Plant Area |
71,000
ft2
|
Annual Production | 1,950
ton
|
Production Hrs. Annual | 4,914
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $117,029 | 879,300 |
kWh
|
$0.13 |
Electricity Demand | $22,076 | 2,958 |
kW-mo/yr
|
$7.46 |
Electricity Fees | $3,924 | - |
|
- |
Natural Gas | $21,262 | 1,552 |
MMBtu
|
$13.70 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,364 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,384 | $27,090 |
$13,526
101,699
kWh
|
$1,858
-
kW-mo/yr
|
|
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,021 | - |
$894
6,873
kWh
|
$127
-
kW-mo/yr
|
|
03 | 2.6212: Turn off equipment during breaks, reduce operating time | $609 | - |
$609
4,576
kWh
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $350 | $200 |
$350
2,693
kWh
|
- | |
TOTAL RECOMMENDED | $17,364 | $27,290 |
$15,379
115,841
kWh
|
$1,985
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $17,364 | $27,290 |
$15,379
115,841
kWh
|
$1,985
-
kW-mo/yr
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs