ITAC Assessment: MA0627
ITAC logo
ITAC Assessment: MA0627
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Ceramic chip capacitors
NAICS 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing
SIC 3675: Electronic Capacitors
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 91,235
ft2
Annual Production 100,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Connecticut

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $712,241 7,367,815
kWh
Electricity Demand $145,813 13,867
kW-mo/yr
LPG $87,857 5,843
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $77,369 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $69,047

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.7241: Install outside air damper / economizer on hvac unit $52,302 $35,000 $52,302
523,022
kWh
- -
02 2.7314: Reduce ventilation air $8,813 $16,000 $8,813
88,132
kWh
- -
03 2.3212: Optimize plant power factor $6,984 $8,550 - $6,984
-
kW-mo/yr
-
04 2.2212: Use minimum safe oven ventilation $6,674 $5,000 $6,674
66,743
kWh
- -
05 2.2612: Use cooling tower water instead of refrigeration $1,648 $4,300 $1,648
16,482
kWh
- -
06 2.2136: Install / repair insulation on steam lines $948 $1,000 - - $948
-
MMBtu
TOTAL RECOMMENDED $77,369 $69,850 $69,437
694,379
kWh
$6,984
-
kW-mo/yr
$948
-
MMBtu
TOTAL IMPLEMENTED $69,047 $60,550 $61,115
611,154
kWh
$6,984
-
kW-mo/yr
$948
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs