Assessment Year | 2008 |
---|---|
Principal Product | Ceramic chip capacitors |
NAICS | 334416: Capacitor, Resistor, Coil, Transformer, and Other Inductor Manufacturing |
SIC | 3675: Electronic Capacitors |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
91,235
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $712,241 | 7,367,815 |
kWh
|
$0.097 |
Electricity Demand | $145,813 | 13,867 |
kW-mo/yr
|
$10.52 |
LPG | $87,857 | 5,843 |
MMBtu
|
$15.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $77,369 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,047 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
---|---|---|---|---|---|---|---|
01 | 2.7241: Install outside air damper / economizer on hvac unit | $52,302 | $35,000 |
$52,302
523,022
kWh
|
- | - | |
02 | 2.7314: Reduce ventilation air | $8,813 | $16,000 |
$8,813
88,132
kWh
|
- | - | |
03 | 2.3212: Optimize plant power factor | $6,984 | $8,550 | - |
$6,984
-
kW-mo/yr
|
- | |
04 | 2.2212: Use minimum safe oven ventilation | $6,674 | $5,000 |
$6,674
66,743
kWh
|
- | - | |
05 | 2.2612: Use cooling tower water instead of refrigeration | $1,648 | $4,300 |
$1,648
16,482
kWh
|
- | - | |
06 | 2.2136: Install / repair insulation on steam lines | $948 | $1,000 | - | - |
$948
-
MMBtu
|
|
TOTAL RECOMMENDED | $77,369 | $69,850 |
$69,437
694,379
kWh
|
$6,984
-
kW-mo/yr
|
$948
-
MMBtu
|
||
TOTAL IMPLEMENTED | $69,047 | $60,550 |
$61,115
611,154
kWh
|
$6,984
-
kW-mo/yr
|
$948
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | LPG Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs