Assessment Year | 2007 |
---|---|
Principal Product | Steel cast products |
NAICS | 333511: Industrial Mold Manufacturing |
SIC | 3544: Special Dies and Tools, Die Sets, Jigs and Fixtures, and Industrial Molds |
Sales Range | $10 M to 50M |
# of Employees | 112 |
Plant Area |
116,620
ft2
|
Annual Production | 5,000
ton
|
Production Hrs. Annual | 4,905
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $658,850 | 5,965,433 |
kWh
|
$0.11 |
Electricity Demand | $157,418 | 37,214 |
kW-mo/yr
|
$4.23 |
Electricity Fees | $46,155 | - |
|
- |
Natural Gas | $242,547 | 19,053 |
MMBtu
|
$12.73 |
LPG | $11,607 | 816 |
MMBtu
|
$14.22 |
Fuel Oil #2 | $43,244 | 2,796 |
MMBtu
|
$15.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $84,629 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7313: Recycle air for heating, ventilation and air conditioning | $67,278 | $157,500 | - | - |
$67,278
-
MMBtu
|
- | |
02 | 2.1135: Repair furnaces and oven doors so that they seal efficiently | $6,543 | $8,000 | - | - |
$6,543
-
MMBtu
|
- | |
03 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $5,346 | - | - | - |
$5,346
-
MMBtu
|
- | |
04 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $3,465 | $2,500 | - | - |
$7,065
-
MMBtu
|
$(-3,600.0) | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,602 | $5,481 |
$1,441
13,100
kWh
|
$161
-
kW-mo/yr
|
- | - | |
06 | 2.2524: Avoid cooling of process streams or materials that must subsequently be heated | $395 | $200 | - | - |
$395
-
MMBtu
|
- | |
TOTAL RECOMMENDED | $84,629 | $173,681 |
$1,441
13,100
kWh
|
$161
-
kW-mo/yr
|
$86,627
-
MMBtu
|
$(-3,600.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs