Assessment Year | 2007 |
---|---|
Principal Product | tissue paper |
NAICS | 322121: Paper (except Newsprint) Mills |
SIC | 2621: Paper Mills |
Sales Range | $1 M to 5M |
# of Employees | 121 |
Plant Area |
208,000
ft2
|
Annual Production | 43,800
ton
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Massachusetts |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $6,189,578 | 46,682,650 |
kWh
|
$0.13 |
Electricity Demand | $346,041 | 76,053 |
kW-mo/yr
|
$4.55 |
Electricity Fees | $848 | - |
|
- |
Fuel Oil #2 | $1,156,108 | 73,065 |
MMBtu
|
$15.82 |
Fuel Oil #6 | $2,981,695 | 342,186 |
MMBtu
|
$8.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,433,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,899,551 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | Wood Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1331: Burn a less expensive grade of fuel | $1,852,277 | $4,120,500 | - | - | - |
$2,980,440
-
MMBtu
|
$(-1,115,663.0)
-
MMBtu
|
$(-12,500.0) | |
02 | 2.2444: Use hot process fluids to preheat incoming process fluids | $653,801 | $423,075 |
$(-8,678.0)
(-65,350)
kWh
|
- |
$662,479
-
MMBtu
|
- | - | - | |
03 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $449,650 | $250,000 | - | - | - |
$449,650
-
MMBtu
|
- | - | |
04 | 2.4323: Use optimum size and capacity equipment | $337,840 | $694,400 |
$321,925
2,424,135
kWh
|
$15,915
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $67,981 | $60,600 |
$64,932
488,949
kWh
|
$3,049
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4321: Upgrade obsolete equipment | $34,468 | $111,500 |
$34,468
259,459
kWh
|
- | - | - | - | - | |
07 | 2.2136: Install / repair insulation on steam lines | $21,165 | $10,000 | - | - | - |
$21,165
-
MMBtu
|
- | - | |
08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,919 | $30,500 |
$14,900
112,000
kWh
|
$1,019
-
kW-mo/yr
|
- | - | - | - | |
TOTAL RECOMMENDED | $3,433,101 | $5,700,575 |
$427,547
3,219,193
kWh
|
$19,983
-
kW-mo/yr
|
$662,479
-
MMBtu
|
$3,451,255
-
MMBtu
|
$(-1,115,663.0)
-
MMBtu
|
$(-12,500.0) | ||
TOTAL IMPLEMENTED | $2,899,551 | $5,359,475 |
$347,715
2,618,244
kWh
|
$15,915
-
kW-mo/yr
|
$662,479
-
MMBtu
|
$3,001,605
-
MMBtu
|
$(-1,115,663.0)
-
MMBtu
|
$(-12,500.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Fuel Oil #2 Savings | Fuel Oil #6 Savings | Wood Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs