Assessment Year | 2006 |
---|---|
Principal Product | Slit plastic and paper films, cable fillers, non-woven films |
NAICS | 326113: Unlaminated Plastics Film and Sheet (except Packaging) Manufacturing |
SIC | 3497: Metal Foil and Leaf |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
52,200
ft2
|
Annual Production | 1,250,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Connecticut |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $333,043 | 3,816,964 |
kWh
|
$0.087 |
Electricity Demand | $79,378 | 8,417 |
kW-mo/yr
|
$9.43 |
Natural Gas | $31,199 | 2,399 |
MMBtu
|
$13.01 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $75,851 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $45,854 | $54,000 |
$50,787
513,000
kWh
|
$19,166
-
kW-mo/yr
|
$(-24,099.0)
-
MMBtu
|
|
02 | 2.2492: Use "heat wheel" or other heat exchanger to cross-exchange building exhaust air with make-up air | $11,356 | $40,000 |
$(-1,782.0)
(-18,000)
kWh
|
$(-340.0)
-
kW-mo/yr
|
$13,478
-
MMBtu
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,050 | $5,000 |
$1,960
19,800
kWh
|
$350
-
kW-mo/yr
|
$2,740
-
MMBtu
|
|
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,398 | $19,100 |
$3,980
40,200
kWh
|
$418
-
kW-mo/yr
|
- | |
05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $3,871 | $7,500 |
$3,871
39,100
kWh
|
- | - | |
06 | 2.4239: Eliminate or reduce compressed air usage | $1,436 | $2,200 |
$901
9,100
kWh
|
$535
-
kW-mo/yr
|
- | |
07 | 2.7243: Improve air circulation with destratification fans / other methods | $1,227 | $3,200 |
$(-257.0)
(-2,600)
kWh
|
$(-38.0)
-
kW-mo/yr
|
$1,522
-
MMBtu
|
|
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,158 | $300 |
$1,158
11,700
kWh
|
- | - | |
09 | 2.2511: Insulate bare equipment | $849 | $600 |
$713
7,200
kWh
|
$136
-
kW-mo/yr
|
- | |
10 | 2.4231: Reduce the pressure of compressed air to the minimum required | $652 | - |
$545
5,500
kWh
|
$107
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $75,851 | $131,900 |
$61,876
625,000
kWh
|
$20,334
-
kW-mo/yr
|
$(-6,359.0)
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs